Tracks damaged
U1 remains closed until the beginning of December
Following the fire on the U1 subway line on Tuesday, the middle section of the line will remain closed until the beginning of December. This is according to an expert opinion from Wiener Linien. 50 meters of track, 25 sleepers and several kilometers of cable need to be replaced.
As reported, the U1 line is interrupted between Schwedenplatz and Südtiroler Platz. Continuous service is not planned until the first week of December. The replacement service will remain in operation until then.
Defective sleepers and cables
After the defective train was removed, the clean-up work began. First, the tunnel walls were checked and the track bed cleaned. "It turned out that a total of around 50 meters of the track had been affected, 15 meters of which were severely damaged. There were defects in sleepers and cable support systems," according to Wiener Linien.
In the coming days, 50 meters of track, 25 sleepers, 400 meters of cable trays and several kilometers of cable will have to be replaced. Due to the limited space available, the damaged infrastructure must first be removed and transported away before the new material can be delivered and installed.
Once the work has been completed, a track measuring car is driven along the route. This checks with millimeter precision that all track dimensions are correct. The final step is to check the track ventilation and the train protection system. If these checks are also positive, the green light can be given for the start of operations. The renovation work is expected to be completed in the first week of December and the U1 will be able to run continuously again, the transport company said in a statement.
Alexandra Reinagl, Managing Director of Wiener Linien: "We are doing everything we can to be able to offer the usual quality of service again as soon as possible."
Silver arrows are being checked
It is still unclear how the fire in the train set started.
"All vehicles are checked at regular intervals, and there are clear legal requirements. Before each journey, the vehicle is checked to ensure it is in good working order, and several safety systems and sensors check the train during operation," says Wiener Linien.
The Silver Arrows are checked in the workshop every six weeks. The annual overhaul takes place once a year. The vehicle is dismantled and all relevant components are metrologically checked and components are routinely replaced. "I have ordered an additional check of all Silver Arrows of the relevant generation," says Reinagl.
This article has been automatically translated,
read the original article here.
Kommentare
Willkommen in unserer Community! Eingehende Beiträge werden geprüft und anschließend veröffentlicht. Bitte achten Sie auf Einhaltung unserer Netiquette und AGB. Für ausführliche Diskussionen steht Ihnen ebenso das krone.at-Forum zur Verfügung. Hier können Sie das Community-Team via unserer Melde- und Abhilfestelle kontaktieren.
User-Beiträge geben nicht notwendigerweise die Meinung des Betreibers/der Redaktion bzw. von Krone Multimedia (KMM) wieder. In diesem Sinne distanziert sich die Redaktion/der Betreiber von den Inhalten in diesem Diskussionsforum. KMM behält sich insbesondere vor, gegen geltendes Recht verstoßende, den guten Sitten oder der Netiquette widersprechende bzw. dem Ansehen von KMM zuwiderlaufende Beiträge zu löschen, diesbezüglichen Schadenersatz gegenüber dem betreffenden User geltend zu machen, die Nutzer-Daten zu Zwecken der Rechtsverfolgung zu verwenden und strafrechtlich relevante Beiträge zur Anzeige zu bringen (siehe auch AGB). Hier können Sie das Community-Team via unserer Melde- und Abhilfestelle kontaktieren.